Trail build report: 30 people, 20 tonnes (start, exit, mway1, east side)

See the complete Croft trail build diary. After low key build days in December (triangle surfacing) and January (triangle woodwork) we had a big day planned. Twenty tonnes of build materials had been delivered on Thursday morning: half a tonne of gabion (rocks) and 19.5 tonnes of type 1 limestone. Our target was to shift all of this …

Trail build report: 30 people, 20 tonnes (start, exit, mway1, east side) Read More »

Trail build report: Sun 15th Jan 2012, Triangle surfacing + exit

Newly surfaced trail from the previous day. We’d made great progress on the previous day. The tasks for this day were to finish off a few patches in the triangle, spread the limestone dust onto the surface and to make more progress with the exit section. Kristian, John Proudman, Gary Lee, Karl and Cameron spent …

Trail build report: Sun 15th Jan 2012, Triangle surfacing + exit Read More »