Trail build report: 11th Jan – rock garden modifications

  • Post author:Rafe
  • Post published:January 11, 2009
  • Post category:Croft Diary
  • Post comments:0 Comments

From the Facebook group: "Phil and myself (Tom) did some odd jobs today. Rearranged the middle section of the first new rock garden so it's a bit wider, did a…

Continue Reading Trail build report: 11th Jan – rock garden modifications

Trail build report: 24th Dec – test ride

  • Post author:Rafe
  • Post published:December 24, 2008
  • Post category:Croft Diary
  • Post comments:0 Comments

Phil and myself (Tom) did a test ride of the trail. Here's our feedback which was posted on the Facebook group at the time: " Phil and myself did a…

Continue Reading Trail build report: 24th Dec – test ride

Trail build report: 21st Dec – first and second rock garden

  • Post author:Rafe
  • Post published:December 21, 2008
  • Post category:Croft Diary
  • Post comments:0 Comments

Phil and myself (Tom) continued our work on the first rock garden feature. We then made a start on the second major rock garden on the trail. We built the…

Continue Reading Trail build report: 21st Dec – first and second rock garden

Trail build report: 20th Dec – first rock garden

  • Post author:Rafe
  • Post published:December 20, 2008
  • Post category:Croft Diary
  • Post comments:0 Comments

Phil and myself (Tom) spent the afternoon working on the first rock garden feature. We did modify it slightly a few weeks after building it by making a bit wider…

Continue Reading Trail build report: 20th Dec – first rock garden

Trail build report: 14th Dec 2008 – flood. Rock moving to Piper’s hill

  • Post author:Rafe
  • Post published:December 14, 2008
  • Post category:Croft Diary
  • Post comments:0 Comments

A deluge of rain meant that some of the woodwork section had floated away. We spent the morning retrieving the missing sections. We tackled the source of the problem by…

Continue Reading Trail build report: 14th Dec 2008 – flood. Rock moving to Piper’s hill

Trail build report: 7th Dec 2008 – South side continued

  • Post author:Rafe
  • Post published:December 7, 2008
  • Post category:Croft Diary
  • Post comments:0 Comments

We'd used the Land Rover to move the red type one stone to the South side of the pitch on the previous day. When we arrived then the piles of…

Continue Reading Trail build report: 7th Dec 2008 – South side continued

Trail build report: 6th Dec 2008 – South side of pitch

  • Post author:Rafe
  • Post published:December 6, 2008
  • Post category:Croft Diary
  • Post comments:0 Comments

We made brilliant progress today, digging out 150m of trail and surfacing about 80% of that, with the necessary materials in place to finish it off on Sunday. This is…

Continue Reading Trail build report: 6th Dec 2008 – South side of pitch

Trail build report: 29th & 30th Nov – West side finished

  • Post author:Rafe
  • Post published:November 29, 2008
  • Post category:Croft Diary
  • Post comments:0 Comments

Saturday 29th Nov 2008 From our Facebook group: "We managed loads this afternoon. There were four of us: Kate and James along with Phil and myself (Tom). We dug out…

Continue Reading Trail build report: 29th & 30th Nov – West side finished

Trail build report: 9th Nov – West side

  • Post author:Rafe
  • Post published:November 9, 2008
  • Post category:Croft Diary
  • Post comments:0 Comments

From our Facebook group: "Phil and myself spent a few hours digging and surfacing today. The gravelled section is now level with the Southern end of the pavillion. We've dug…

Continue Reading Trail build report: 9th Nov – West side

Trail build report: 8th Nov – gravel moving and exit rock

  • Post author:Rafe
  • Post published:November 8, 2008
  • Post category:Croft Diary
  • Post comments:0 Comments

This was the first time that Rafe joined us with his Land Rover. After receiving a sense of humour upgrade then Rafe went on to be a founding member of…

Continue Reading Trail build report: 8th Nov – gravel moving and exit rock
  • 1
  • 2
  • Go to the next page

Join MB Swindon

Membership is just £10 a year and supports the Croft Trail. Join online now!

Discount Codes

Members can find codes for online discounts in the Members Only Area.

Join the conversation

Join the Facebook group and chat with other mountain bikers in Swindon.

Mountain biking is a risk-assumed sport so please take care, ensure your bike is properly maintained and wear appropriate clothing and a helmet. Riding the Croft Trail or any other route mentioned on this site is done so at your own risk. This includes attending rides listed in our events calendar which are, unless stated otherwise, arranged by volunteers not trained leaders. If in doubt about your abilities on a particular section, get off and walk and consider getting professional training.

Copyright [oceanwp_date] - MB Swindon
Close Menu