Trail build report: 13th Sept 2009
We tidied up the trail on the South side of the pitch. This was originally build in December 2008. The line was straightened out a bit and a new berm…
We tidied up the trail on the South side of the pitch. This was originally build in December 2008. The line was straightened out a bit and a new berm…
A deluge of rain meant that some of the woodwork section had floated away. We spent the morning retrieving the missing sections. We tackled the source of the problem by…
We'd used the Land Rover to move the red type one stone to the South side of the pitch on the previous day. When we arrived then the piles of…
We made brilliant progress today, digging out 150m of trail and surfacing about 80% of that, with the necessary materials in place to finish it off on Sunday. This is…
It's still early days on the trail and the current aim is to get the basic route finished. Some of the route is a bit bare, and there's not enough…